1. INTRODUCTION

The Bahrain International Airport is scheduled to go through construction phase due to the expansion of the terminal building and associated facilities. This may impose certain constraints on a number of ground areas within the airport. And temporarily limit the functionality of those areas to varying extent. Users are therefore required to understand and become fully acquainted with the affected areas, as indicated in the paragraphs hereunder. This AIP SUP contains charts attachments A.

2. Scope of Constraints

2.1 Southern Restriction:

2.1.1 At 420M from RWY 30R/12L C/L running parallel along the runway to the end of the runway from the southern side, work-in-progress will take place with an obstacle height of not more than 90M.

Name LOCATION Height (M) Annex 14 Surface
TC06Mobile Crane Operations will take place in front of the Control Tower, at a distance of 420M to the south of RWY 30R/12L C/L running parallel along the entire length of the runway.85Inner Horizontal

Affected Areas: ALL RWY’s

Note: For Airport New IAC Charts And Minima’s Refer To AIRAC AIP.

Figure 1. 4 TEMPO Cranes OBST Attachment A